Company or firm · first RERA registration 2017
Shree Builders And Developers
Of 2 registrations whose promised date has arrived, 2 were never extended past it (100%).
Projects22 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
No registration has been extended past its RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree ShilpP52700010339 | Karanje Tarf Satara (Ct) | Certificate Signed | 31 Jul 2019 | 31 Jul 2019 | On date |
| Shree YashP52700021875 | Karanje Tarf Satara (Ct) | Certificate Signed | 31 Jul 2025 | 31 Jul 2025 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology