Company or firm · first RERA registration 2025
Shree Balaji Associates
None of 1 registration has reached its promised completion date yet.
Projects11 RERA registration
Kept RERA dateNone due yet
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 1 moved past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sentosa EdgePM1260002501839 | Punawale | Certificate Signed | 30 Jun 2030 | 30 Oct 2030 | +4 mo |