Deedo IDDD-73NHOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.
Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay24 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shhraddha Ellegance Building BP52600000096 | Solapur (M Corp.) | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
| Shhraddha Ellegance Building CP52600000708 | Solapur (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Shhraddha Ellegance Building HP52600048179 | Solapur (M Corp.) | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology