Shanti Enterprise
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 53 mo late.
Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay53 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rishita ApartmentP51700005397 | Mirabhayandar (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| SwashrayP51800018547 | Borivali | Certificate Signed | 30 May 2022 | 31 Dec 2022 | +53 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology