Company or firm · first RERA registration 2017
Shah And Daswani
Deedo IDDD-98GYOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay12 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| KashidhamP51700011016 | Thane (M Corp.) | Certificate Signed | 31 Dec 2017 | 31 Dec 2018 | +12 mo |
| Kashidham - Row HouseP99000022036 | Palghar | Certificate Signed | 28 Aug 2022 | 28 Aug 2022 | On date |
| Kashidham NXP99000048005 | Vasai Virar City (M Corp) | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology