Individual promoter · first RERA registration 2024
Seema Ramesh Kadav
Deedo IDDD-6TVGNone of 2 registrations has reached its promised completion date yet.
Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Arya ApartmentP51700055393 | Shahapur (Ct) | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Sai Anand ApartmentPR1330002601798 | Cherpoli | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology