Sbm Properties
Deedo IDDD-HN8WOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 34 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sbm MyraP52100004121 | Haveli | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Sbm AvivaP52100018712 | Hinjavadi (Ct) | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +34 mo* |
Sbm Properties, in questions
Does Sbm Properties finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 34 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sbm Properties registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Sbm Properties have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
