Skip to content
Company or firm · first RERA registration 2017

Satyam Homes

Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%).

Projects12 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Satyam Homes developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

2 registrations of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Signature DesireP52000001892HaliwaliCertificate Signed30 Jun 201930 Jun 2022+36 mo
Signature DesireP52000016954HaliwaliCertificate Signed30 Dec 202231 Dec 2023+12 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology