Company or firm · first RERA registration 2017

Sarwdnya Buildcon

Deedo IDDD-1733

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 43 mo late.

Projects44 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay43 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Gokul PlazaP51600005838Nashik (M Corp.)Lapsed31 Dec 201930 Dec 2021+82 mo*
Shri Krishna DarshanP51600032470Nashik (M Corp.)Certificate Signed31 Dec 202931 Dec 2029On date
Shri Krishna TowerP51600050440Nashik (M Corp.)Certificate Signed31 Dec 202731 Dec 2027On date
Shri Krushna LuxriyaP51600079977Nashik (M Corp.)Certificate Signed31 Dec 202830 Apr 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology