Individual promoter · first RERA registration 2021
Sarfaraz Allauddin Barchi
Deedo IDDD-HXAFOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 27 mo late.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay27 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| AL Awwal HeightsP52600032256 | Solapur North | Certificate Signed | 1 Jan 2025 | 1 Jan 2025 | +21 mo* |
| Barchi AvenuoP52600046331 | Solapur (M Corp.) | Certificate Signed | 1 Jan 2024 | 1 Jan 2024 | +33 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology