Individual promoter · first RERA registration 2021
Sanjesh Gopal Patkar
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 20 mo — longer than Maharashtra's 4 mo.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay20 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 1 moved past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Hem Mit ApartmentP51700028668 | Ambarnath (R) | Certificate Signed | 30 Jun 2023 | 28 Feb 2025 | +20 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology