Sanjeet Buildcon
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 54 mo late.
Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay54 mowhen late
Flats sold, all time16registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sarthak ResidencyP52100011895 | Dhanori | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Asha ResidencyP52100021210 | Dhanori | Certificate Signed | 30 Apr 2022 | 29 Apr 2023 | +54 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology