Company or firm · first RERA registration 2024
Sanghvip Builders LLP
None of 4 registrations has reached its promised completion date yet.
Projects44 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
4 registrations of 4 moved past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sanghvi AriaPM1180002400013 | Andheri | Certificate Signed | 31 May 2027 | 30 Sep 2027 | +4 mo |
| Sanghvi CrystalPM1180002400050 | Borivali | Certificate Signed | 29 Feb 2028 | 29 Jun 2028 | +4 mo |
| Sanghvi TirthPR1180002502768 | Kondivita | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
| Sanghvi Boulevard 97 PrismPR1180002600429 | Malad | Certificate Signed | 31 Dec 2032 | 30 Apr 2033 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology