Company or firm · first RERA registration 2019
Sanghvi Parsssva Enterprise LLP
None of 2 registrations has reached its promised completion date yet.
Projects22 RERA registrations
Kept RERA dateNone due yet
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
No registration has been extended past its RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sanghvi Parsssva ExcellenseaP51900020397 | Ward Abcd | Not on record | 31 Mar 2027 | — | On date |
| Sanghvi Parsssva EternityP51900046223 | Ward Abcd | Not on record | 31 Dec 2028 | — | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology