Company or firm · first RERA registration 2017
Sandeep Construction Company
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 50 mo late.
Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay50 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Parth EstateP52100003629 | Pune (M Corp.) | Certificate Signed | 22 Jan 2021 | 22 Jan 2021 | On date |
| Parth Estate Building DP52100017861 | Pune (M Corp.) | Certificate Signed | 28 Aug 2022 | 28 Aug 2022 | +50 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology