Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 19 mo late.

Projects45 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay19 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
You57P52100021770ManCertificate Signed30 Dec 202230 Dec 2022On date
You57 Tower BP52100025947MulshiCertificate Signed30 Sep 202330 Sep 2023On date
You57P52100049250ManCertificate Signed31 Mar 202531 Mar 2025+19 mo*
You57 Amenity BuildingP52100049285ManCertificate Signed31 Mar 202431 Mar 2025+31 mo*
You57 Tower DPR1264042501139ManCertificate Signed29 Feb 202829 Jun 2028+4 mo