Sakshi Builders
Company or firm · 6 projects · 6 MahaRERA registrations · 2 reported completed
Projects66 RERA registrations
Completed2as reported on MahaRERA project pages
Kept RERA date100%5 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sakshi Varad Vinayak Phase IIP51500006213 | Aurangabad (M Corp.) | 2017 | Completed | 30 Oct 2018 | — | On date |
| Radhakrishna Residency Phase IIP51500006840 | Aurangabad (M Corp.) | 2017 | Not reported | 30 Dec 2021 | — | On date |
| Radhakrishna Residency Phase IIIP51500017900 | Aurangabad (M Corp.) | 2018 | Not reported | 30 Mar 2021 | — | On date |
| Vrundavan ApartmentP51500026897 | Aurangabad (M Corp.) | 2020 | Not reported | 30 Jun 2023 | — | On date |
| Parvati EnclaveP51500029599 | Aurangabad (M Corp.) | 2021 | Completed | 30 Dec 2024 | — | On date |
| Kashi VrundavanP51500078996 | Aurangabad (M Corp.) | 2025 | Not reported | 31 Dec 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology