Sakshi Varad Vinayak Phase II

Completed

Aurangabad (M Corp.), Aurangabad 431001 |Promoter: Sakshi Builders

Residential / Group HousingRERAP51500006213
14 Aug 2017Registered with MahaRERA
30 Oct 2018Promised completion
3Buildings
24Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
3
Unit types
Row house, Flat24 units in all
Land area for this project
1,583 sq m (17,036 sq ft)
Permissible built-up area
1,677 sq m (18,056 sq ft)
Sanctioned built-up area
1,677 sq m (18,056 sq ft)
Address
Plot No 6 7 8 Gut No 26/3, Jatwada Road, AurangabadPIN 431001
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.10472, 72.82683
Sakshi Varad Vinayak Phase II is at latitude 19.10472, longitude 72.82683.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Oct 2018

The latest completion date on record passed 8 years ago.

Registered
14 Aug 2017
Promised
30 Oct 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150000621314 Aug 201730 Oct 2018—Sakshi BuildersProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
C Building 14 To 2047
D Building 21 To 2747
E Building 1 To 10510

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

24 units registered

Row house · 14 unitsFlat · 10 units
BuildingTypeCarpet areaUnits
C Building 14 To 20Row house81.2 sq m · 874 sq ft7
D Building 21 To 27Row house81.24 sq m · 874 sq ft7
E Building 1 To 10Flat33.8 sq m · 364 sq ft3
E Building 1 To 10Flat37.31 sq m · 402 sq ft3
E Building 1 To 10Flat38.51 sq m · 415 sq ft3
E Building 1 To 10Flat55.62 sq m · 599 sq ft1

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
C Building 14 To 20Closed/Covered00007
C Building 14 To 20Open Space00000
D Building 21 To 27Closed/Covered00007
D Building 21 To 27Open Space00000
E Building 1 To 10Closed/Covered000010
E Building 1 To 10Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

C Building 14 To 20

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

D Building 21 To 27

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

E Building 1 To 10

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsPAVER BLOCK/ CONCRETE100%
  • Water SupplyONE COMMON BOREWELL100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEWERAGE LINE100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingFEW PLANTETION100%
  • Street LightingLED/CFL LIGHTS100%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRAIN WATER HARVESTING100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

29 documents held by Deedo, 43 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Proforma of Allotment letterarvi-0009-ilovepdf-compressed.pdf · uploaded 30 Jul 2017View
  • Copy of the legal title reportsearch report.pdf · uploaded 30 Jul 2017View
  • Declaration in FORM BFORM B sakshi.pdf · uploaded 30 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sakshi Architecht scan copy.pdf · uploaded 30 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 30 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate scan sakshi.pdf · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)All plan.pdf · uploaded 30 Jul 2017View
  • Details of encumbrancesNon Ecumbernace performa Scan copy Sakshi Builders.pdf · uploaded 30 Jul 2017View
  • Copy of Layout Approval (in case of layout)Sakshi Builders Layout.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)Sakshi Builders Layout Order.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)IMG.pdf · uploaded 14 Dec 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)IMG (1).pdf · uploaded 14 Dec 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)SAKSHI VARAD VINAYAK - ARCHI CERTIFICATE.pdf · uploaded 13 Feb 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)SAKSHI VARAD VINAYAK - ENG CERTIFICATE.pdf · uploaded 13 Feb 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sakshi Varad Vinayak - Architect Certificate.pdf · uploaded 28 May 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate - sakshi varad vinayak.pdf · uploaded 5 Jun 2018View
  • Certificates of CA (Form 5)FORM-5 Sakshi Varad Vinayak Phase-2.pdf · uploaded 15 Nov 2018View
  • Certificates of Architect (Form 4)IMG.pdf · uploaded 27 Dec 2018View
  • OtherOC.pdf · uploaded 27 Dec 2018View
  • OtherIMG_106.pdf · uploaded 27 Dec 2018View
  • OtherIMG_107.pdf · uploaded 27 Dec 2018View
  • OtherIMG_108.pdf · uploaded 27 Dec 2018View
  • OtherIMG_109.pdf · uploaded 27 Dec 2018View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)'' Sakshi varad vinayak phase-2 ''.pdf · uploaded 30 Nov 2019View
  • Status of Formation of Legal Entity (Society/Co Op etc.)'' SAKSHI VARADVINAYAK PHASE -II '' Legal Entity.pdf · uploaded 17 Sep 2021View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Sakshi Varadvinayak Phase -II.pdf · uploaded 17 Sep 2021View
  • Status of ConveyanceStatus of Conveyance_Sakshi Varadvinayak Ph-II.pdf · uploaded 7 Feb 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development1 Other (1).pdf · uploaded 6 Dec 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development2 Other.pdf · uploaded 6 Dec 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development3 Other.pdf · uploaded 6 Dec 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development4 Other.pdf · uploaded 6 Dec 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development5 Other.pdf · uploaded 6 Dec 2024View

Promoter documents

  • Legal Title reportsearch report.pdf · uploaded 30 Jul 2017View
  • Declaration Form BFORM B sakshi.pdf · uploaded 30 Jul 2017View

Technical documents

  • Building Plan ApprovalAll plan.pdfView
  • Layout ApprovalSakshi Builders Layout.pdfView
  • Layout ApprovalSakshi Builders Layout Order.pdfView

Other legal documents

Proforma allotment letter

  • Proforma allotment letterarvi-0009-ilovepdf-compressed.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

PLOT NO 6 7 8 GUT NO 26/3

As published on MahaRERA's project page

PLOT NO 6 7 8 GUT NO 26/3

Boundaries

North
6 Mtrs Road
South
Survey No 26 Part Arvee Constructions
East
Compound Wall
West
Internal Pathway

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAvinash B Pawar—
EngineerPrasad Arun Aphale—
OtherSaksh Constructions—

Source: MahaRERA project page. Contact details are not shown.