Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).

Projects22 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Sairaj Realtors developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Sai VillaP52000031365WahalCertificate Signed31 Dec 202331 Dec 2023On date
Sai IconicP52000079188PanvelCertificate Signed31 Dec 202730 Apr 2028+4 mo