Company or firm · first RERA registration 2019

Sai Tara Builders

Deedo IDDD-KX19

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay18 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shri KrishnleelaP52000022111Vadghar (Ct)Certificate Signed14 Jan 202314 Jan 2023On date
Sai BugaiP52000022228Vadghar (Ct)Certificate Signed14 Jul 20214 Jan 2023+18 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology