Sai Smaran Infra And Developers
Deedo IDDD-7T6WOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 49 mo late.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay49 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Sai ManasRegulatory order: PROJECT NAME: SAI MANAS (Regulatory Case No. 376 OF 2025) dated 18 June, 2025. | 18 Jun 2025 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai ManasP52000008081 | Pashane | Certificate Signed | 31 Dec 2018 | 30 Jun 2026 | +94 mo* |
| SatyanathP52000026447 | Karjat | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology