Company or firm · first RERA registration 2018

Sai Siddha Associates

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 13 mo late.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay13 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kanak ResidencyP52100015673Pimpri Chinchawad (M Corp.)Certificate Signed30 Jun 202230 Jun 2022On date
Kanak Residency Phase IIP52100033344KivaleCertificate Signed24 Dec 202422 Dec 2025+22 mo*
LenoraPR1260002500833KiwaleCertificate Signed25 Dec 202925 Apr 2030+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology