Company or firm · first RERA registration 2018
Sai Siddha Associates
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 13 mo late.
Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay13 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kanak ResidencyP52100015673 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | On date |
| Kanak Residency Phase IIP52100033344 | Kivale | Certificate Signed | 24 Dec 2024 | 22 Dec 2025 | +22 mo* |
| LenoraPR1260002500833 | Kiwale | Certificate Signed | 25 Dec 2029 | 25 Apr 2030 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology