Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 68 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay68 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sriroz Paradise Phase 4P52100013743HaveliCertificate Signed28 Feb 202128 Feb 2021+68 mo*

Sai Sane Developers, in questions

Does Sai Sane Developers finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 68 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sai Sane Developers registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Sai Sane Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology