Skip to content
Company or firm · first RERA registration 2017

Sai Rachana Life Spaces

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay8 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sai SanskrutiP52100007881YawalewadiCertificate Signed30 Jun 202130 Jun 2022+12 mo
Sai Sanskruti Phase 2PM1261012500900YawalewadiCertificate Signed31 Dec 203030 Apr 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology