Company or firm · first RERA registration 2017
Sai Pushp Enterprises
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects22 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases1no insolvency
No registration has been extended past its RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Tokyo Bay Phase - 2CDeregistered: Tokyo Bay Phase - 2C | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tokyo Bay Phase - 1P51700000618 | Thane (M Corp.) | Certificate Signed | 30 Oct 2023 | 30 Oct 2023 | On date |
| Tokyo Bay Phase - 2CP51700020265 | Thane (M Corp.) | Certificate Signed | 28 Feb 2027 | 28 Feb 2027 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology