Company or firm · first RERA registration 2018

Sai Properties

Of 4 registrations whose promised date has arrived, 4 kept it (100%).

Projects55 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vrindavan BhavanaP51700018376Badlapur (M Cl)Certificate Signed30 Sep 202030 Sep 2020On date
Vrindavan AnantamP51700023570Badlapur (M Cl)Certificate Signed30 Jun 202230 Jun 2022On date
Vrindavan JyotP51700048090Badlapur (M Cl)Certificate Signed31 Oct 202331 Oct 2023On date
Vrindavan NisargP51700048292Badlapur (M Cl)Certificate Signed31 Oct 202431 Oct 2024On date
Vrindavan NidhiPM1330002600131KatrapCertificate Signed31 Dec 202730 Apr 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology