Company or firm · first RERA registration 2018
Sai Nandan Buildcon
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 28 mo late — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay28 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Eka VallyP52100017628 | Karla | Certificate Signed | 28 Aug 2022 | 10 Dec 2024 | +28 mo |
| Ramana Eka ValleyP52100032951 | Karla | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
