Sai Nandan Buildcon

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 28 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay28 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Eka VallyP52100017628KarlaCertificate Signed28 Aug 202210 Dec 2024+28 mo
Ramana Eka ValleyP52100032951KarlaCertificate Signed31 Dec 202431 Dec 2024On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology