Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).

Projects11 RERA registration
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases1no insolvency
Sai Jyot Enterprises developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

No registration has been extended past its RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Registration revokedSai Jyot EnterprisesRegistration revoked / ab initio void: VINAYAK VATIKA BUILDERS AND DEVELOPERS · may refer to a related projectNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Sai Jyot EnterprisesP51700032343KalyanCertificate Signed31 Dec 202531 Dec 2025On date