Company or firm · first RERA registration 2018
Sai Infra
Deedo IDDD-TXESOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 40 mo late.
Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay40 mowhen late
Flats sold, all time1registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| The Greater GoodP52100015361 | Mohammadwadi | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | +52 mo* |
| The Greater GoodP52100015734 | Mohammadwadi | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +28 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology