Company or firm · first RERA registration 2020
Sai Dreams Associates
None of 1 registration has reached its promised completion date yet.
Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
No registration has run past its RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Quarterly progress report not filed | Sai Villas Building-A, Building-B And Building-CQuarterly progress report not filed: SAI VILLAS BUILDING-A, BUILDING-B AND BUILDING-C | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai Villas Building-A, Building-B And Building-CP52700025465 | Phaltan | Certificate Signed | 30 May 2028 | 30 May 2028 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology