Company or firm · first RERA registration 2017
Sahyog Homes Limited
Deedo IDDD-QMTTOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 27 mo late — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay27 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | VeronaRegulatory order: PROJECT NAME: VERONA (Regulatory Case No. 340 OF 2025) dated 07 March, 2025. | 7 Mar 2025 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| OshiP51800002965 | Andheri | Certificate Signed | 30 Dec 2022 | 30 Jun 2024 | +18 mo |
| VeronaP51800003040 | Andheri | Certificate Signed | 31 Dec 2024 | 31 Dec 2027 | +36 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology