Company or firm · first RERA registration 2017

Sahyog Homes Limited

Deedo IDDD-QMTT

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 27 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay27 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
OshiP51800002965AndheriCertificate Signed30 Dec 202230 Jun 2024+18 mo
VeronaP51800003040AndheriCertificate Signed31 Dec 202431 Dec 2027+36 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology