Sahyadri Builders & Developers

Deedo IDDD-WYS0

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 23 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay23 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Anandvan Phase IIP52700003940Wai (Rural)Certificate Signed30 Dec 202430 Nov 2026+23 mo
Anandvan Phase 1P52700007067Wai (Rural)Certificate Signed30 Dec 202430 Nov 2026+23 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology