Company or firm · first RERA registration 2017

Sahana-Sheth

Deedo IDDD-SEWY

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 34 mo late.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay34 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Beaumonte Tower AP51900008720Ward FnorthCertificate Signed30 Dec 202330 Dec 2023+34 mo*
Beaumonte Tower B Phase 1 Sale Building No 10P51900015342Ward FnorthCertificate Signed30 Dec 202430 Dec 2024On date
Beaumonte Tower C Sale Bndg No 10 -Wing CP51900050715BhosariCertificate Signed30 Apr 202830 Apr 2028On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology