Skip to content
Individual promoter · first RERA registration 2018

Sachin Jayram Nalawade

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 9 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay9 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Jayram ResidencyP52100016883DholwadCertificate Signed31 Dec 201931 Jan 2021+13 mo
Chhatrapati SquareP52100052511OturCertificate Signed25 Dec 202625 Apr 2027+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology