Company or firm · first RERA registration 2017
Sachin Enterprises
Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 18 mo — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay18 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Horizon Classique-IP51700006371 | Thane (M Corp.) | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Horizon Classique-2P51700015081 | Thane (M Corp.) | Certificate Signed | 30 Jun 2021 | 30 Dec 2022 | +18 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology