Company or firm · first RERA registration 2025

S R Choudhari Construction

Deedo IDDD-4SMN

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rudra ResidencyPR1330002501411Kalyan-Dombivali (M Corp.)Certificate Signed31 Aug 202831 Dec 2028+4 mo

S R Choudhari Construction, in questions

Does S R Choudhari Construction finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has S R Choudhari Construction registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does S R Choudhari Construction have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.