Company or firm · first RERA registration 2017

Runwal Construction Private Limited

Of 4 registrations whose promised date has arrived, 1 were never extended past it (25%). When extended, the date moved a median 4 mo — the same as Maharashtra's 4 mo.

Projects910 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Runwal Construction Private Limited developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

8 registrations of 10 moved past the RERA date

Months late against the original RERA promise, per registration

10 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Runwal SereneP51800000347KurlaCertificate Signed31 May 201931 May 2019On date
Runwal PearlP51700001383Thane (M Corp.)Certificate Signed31 May 201931 Dec 2024+67 mo
The SanctuaryP51800012621KurlaCertificate Signed31 Jul 202831 Jul 2028On date
The SanctuaryP51800025926KurlaCertificate Signed30 Sep 202630 Jan 2027+4 mo
The SanctuaryP51800029440KurlaCertificate Signed30 Sep 202630 Jan 2027+4 mo
The Sanctuary - Tower 2P51800032538KurlaCertificate Signed31 Mar 202731 Jul 2027+4 mo
Code Name-EnchantedP51700033799Thane (M Corp.)Certificate Signed30 Jun 202830 Oct 2028+4 mo
Runwal Lands EndP51700046298Thane (M Corp.)Certificate Signed30 Jun 202930 Oct 2029+4 mo
Runwal Lands End - BreezeP51700056121Thane (M Corp.)Certificate Signed30 Apr 203130 Aug 2031+4 mo
Runwal Lands End- SkyePR1330002502164KolshetCertificate Signed30 Sep 203030 Jan 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology