Company or firm · first RERA registration 2017
Runwal Construction Private Limited
Of 4 registrations whose promised date has arrived, 1 were never extended past it (25%). When extended, the date moved a median 4 mo — the same as Maharashtra's 4 mo.
Projects910 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
8 registrations of 10 moved past the RERA date
Months late against the original RERA promise, per registration
10 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Runwal SereneP51800000347 | Kurla | Certificate Signed | 31 May 2019 | 31 May 2019 | On date |
| Runwal PearlP51700001383 | Thane (M Corp.) | Certificate Signed | 31 May 2019 | 31 Dec 2024 | +67 mo |
| The SanctuaryP51800012621 | Kurla | Certificate Signed | 31 Jul 2028 | 31 Jul 2028 | On date |
| The SanctuaryP51800025926 | Kurla | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
| The SanctuaryP51800029440 | Kurla | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
| The Sanctuary - Tower 2P51800032538 | Kurla | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| Code Name-EnchantedP51700033799 | Thane (M Corp.) | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 mo |
| Runwal Lands EndP51700046298 | Thane (M Corp.) | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 mo |
| Runwal Lands End - BreezeP51700056121 | Thane (M Corp.) | Certificate Signed | 30 Apr 2031 | 30 Aug 2031 | +4 mo |
| Runwal Lands End- SkyePR1330002502164 | Kolshet | Certificate Signed | 30 Sep 2030 | 30 Jan 2031 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology