Rohan Gruh Nirman
Deedo IDDD-QP3EOf 1 registration whose promised date has arrived, 1 kept it (100%).
Projects11 RERA registration
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
No registration has run past its RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Suo motu order | Siddharth ApartmentSuo motu order: Secretary, MahaRERA Versus Rohan Gruh Nirman (Suo Motu Case No. 52 of 2020) dated 10th February 2020 | 11 Feb 2020 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Siddharth ApartmentP51700013427 | Badlapur (M Cl) | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology