Rna Corp Pvt. Ltd
Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%).
Projects12 RERA registrations
Kept RERA date50%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases12includes insolvency
1 registration of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
Show all 12 casesShow fewer
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tower A to D on CTS no 104pt, 106pt, 224/1A, 224/1B in Village Ghodbunder, Mira RoadP51700004482 | Mira Bhayandar (M Corp.) | Certificate Signed | 31 Jul 2019 | 31 Jul 2019 | On date |
| Tower A to D on CTS no 104pt, 106pt, 224/1A, 224/1B in Village Ghodbunder, Mira RoadP51700008296 | Mira Bhayandar (M Corp.) | Lapsed | 31 Jul 2018 | 31 Jul 2019 | +12 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology