Skip to content
Company or firm · first RERA registration 2025

Ritesh Futarmal Doshi

Deedo IDDD-AF9J

None of 2 registrations has reached its promised completion date yet.

Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shree Sadguru Krupa Mandavkar ComplexPM1270002501891NagothaneCertificate Signed30 Jun 202730 Oct 2027+4 mo
Vijayshree ApartmentPM1270002601733NagothaneCertificate Signed30 Sep 202730 Sep 2027On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology