Rishabraj Estate Developers Pvt Ltd

Deedo IDDD-F8NE

Of 6 registrations whose promised date has arrived, 3 kept it (50%). The rest ran a median 4 mo late.

Projects1414 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

10 registrations of 14 ran past the RERA date

Months late against the original RERA promise, per registration

14 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dahisar Sunderbaug co-op housing society ltd.P51800002464BorivaliCertificate Signed31 Dec 201831 Dec 2019+12 mo
Das Bhavan CHSLP51800007281BorivaliCertificate Signed31 Dec 201731 Dec 2018+12 mo
63 Goldmedal AvenueP51800027330BorivaliCertificate Signed30 May 202730 Sep 2027+4 mo
Rishabraj AgnelP51800030530BorivaliCertificate Signed31 Aug 202431 Aug 2024On date
Rishabraj SujaiP51800031075BorivaliCertificate Signed31 Aug 202431 Aug 2024On date
Blue LotusP51800033826AndheriCertificate Signed31 Dec 202531 Dec 2025On date
Rishabraj PhoenixP51800033878BorivaliCertificate Signed28 Feb 202728 Feb 2027On date
Rishabraj ChambersP51800045471BorivaliCertificate Signed31 Dec 202531 Dec 2025+10 mo*
Rishabraj AstralP51800077784EksarCertificate Signed31 Aug 202931 Dec 2029+4 mo
Rishabraj CeramontPM1180002500260ValnaiCertificate Signed31 Dec 203130 Apr 2032+4 mo
Rishabraj Forest FrontPM1180002501049KanheriCertificate Signed31 Dec 202830 Apr 2029+4 mo
Rishabraj AvyaanaPM1180002501823Pahadi-GoregaonCertificate Signed31 Dec 202930 Apr 2030+4 mo
H. Rishabraj TowersPM1180002502294BorivaliCertificate Signed31 Dec 203230 Apr 2033+4 mo
Rishabraj ArhamPM1180002502974MaladCertificate Signed30 Jun 202930 Oct 2029+4 mo
Show all 14 registrationsShow fewer
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology