Company or firm · first RERA registration 2017
Renaissance Spaces
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 19 mo late.
Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay19 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| 7th Floor - C Wing - The Baya GoldspotP51800008945 | Andheri | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +34 mo* |
| Floors 8 and 9 - The Baya GoldspotP51800020972 | Andheri | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| The Baya SunriseP51900055576 | Ward Fsouth | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology