Skip to content
Company or firm · first RERA registration 2017

Renaissance Spaces

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 19 mo late.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay19 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
7th Floor - C Wing - The Baya GoldspotP51800008945AndheriCertificate Signed30 Dec 202330 Dec 2023+34 mo*
Floors 8 and 9 - The Baya GoldspotP51800020972AndheriCertificate Signed30 Dec 202330 Dec 2023On date
The Baya SunriseP51900055576Ward FsouthCertificate Signed31 Dec 202930 Apr 2030+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology