Company or firm · first RERA registration 2017

Rdb Mumbai Infrastructures Private Limited

Deedo IDDD-XDXV

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay24 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Regent Orchid - Hema Niwas CHSLP51800011724AndheriCertificate Signed30 Sep 201830 Sep 2019+12 mo
Regent Heights-New Ganga Niwas CHSLP51800011798AndheriCertificate Signed30 Jun 201930 Jun 2022+36 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology