Company or firm · first RERA registration 2017
Ratan Housing Development Limited
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 22 mo late.
Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay22 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Ratan Neptune Phase 3Deregistered: Ratan Neptune Phase 3 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ratan Neptune Phase 2P52100001790 | Pune (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Ratan Neptune Phase 3P52100022269 | Pune (M Corp.) | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | +22 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology