Company or firm · first RERA registration 2017

Ranjekar Realty

Deedo IDDD-58EJ

Of 5 registrations whose promised date has arrived, 4 kept it (80%). The rest ran a median 6 mo late — longer than Maharashtra's 4 mo.

Projects55 RERA registrations
Kept RERA date80%Maharashtra: 73%
Median delay6 mowhen late · Maharashtra: 4 mo
Flats sold, all time1registered sale deeds
Regulatory cases0none on record

1 registration of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
UmangP52100001862ParvatiCertificate Signed31 Dec 201731 Dec 2017On date
MeghmanasP52100002654Pune (M Corp.)Certificate Signed31 Dec 201731 Dec 2017On date
BhagyashreeP52100015709KothrudCertificate Signed30 Oct 202130 Oct 2021On date
MeghrajshreeP52100019354KothrudCertificate Signed30 Oct 202230 Oct 2022On date
YashP52100030981Pune (M Corp.)Certificate Signed30 Jun 202331 Dec 2023+6 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology