Of 7 registrations whose promised date has arrived, 7 kept it (100%).

Projects1010 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 10 ran past the RERA date

Months late against the original RERA promise, per registration

10 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
MayankP52100022751GhorpadiCertificate Signed30 Dec 202330 Dec 2023On date
ParimalP52100023048KothrudCertificate Signed30 Dec 202230 Dec 2022On date
AseemP52100023060GhorpadiCertificate Signed30 Dec 202330 Dec 2023On date
Seeta-GovindP52100027756Pune (M Corp.)Certificate Signed1 Nov 20251 Nov 2025On date
Sharawati ApartmentsP52100030474KothrudCertificate Signed31 Dec 202431 Dec 2024On date
BuniyadP52100051468Karve NagarCertificate Signed30 Jun 202630 Jun 2026On date
YashodhanP52100051695KothrudCertificate Signed30 Jun 202630 Jun 2026On date
Sindhu ApartmentsPR1260002500540Karve NagarCertificate Signed30 Sep 202830 Jan 2029+4 mo
Vishwanjali LaxmiPR1260002500695Sadashiv PethCertificate Signed30 Oct 202828 Feb 2029+4 mo
Shwetambarishree Co-operative Housing Society LimitedPR1260002502012KothrudCertificate Signed30 Mar 202930 Jul 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology