Individual promoter · first RERA registration 2023

Raj Raju Bhoyar

Deedo IDDD-043E

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 14 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay14 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Maa Jagdamba Nagari Phase IP50500049417ChhatrapurCertificate Signed31 Dec 202830 Apr 2029+4 mo
Maa Jagdamba Nagari Phase IIIP50500056445Mohgaon (Bhadade)Certificate Signed31 Oct 202431 Oct 2025+24 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology