Company or firm · first RERA registration 2017
Raj Corporation
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 10 mo late.
Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay10 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Amakin Mohammadiya Complex Phase IIIP51700010706 | Kalyan | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Rajlaxmi ResidencyP51800031414 | Andheri | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +10 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology