Individual promoter · first RERA registration 2019
Rahul Hanumant Satav
Deedo IDDD-M1TQOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 25 mo late.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay25 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Lonavalas Finest Phase 1P52100021847 | Waksai | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +46 mo* |
| Lonavala's Finest Phase2P52100029628 | Waksai | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology