Skip to content
Company or firm · first RERA registration 2017

R. H. Associates

Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
R. H. Associates developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 3 moved past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Renuka HeightsP52100011243JalochiCertificate Signed13 Mar 202013 Mar 2020On date
Gurukrupa ResidencyP52100053180JalochiCertificate Signed31 Dec 202730 Apr 2028+4 mo
Gurukrupa HeightsP52100079412JalochiCertificate Signed1 Feb 20281 Feb 2028On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology